Construction Update - July 16, 2025
Recently, the contractor shifted traffic to the Stage 3 traffic pattern with users traveling on the west side of the road north of 7th Street and on the east side of the road south of 7th Street. This is a huge step towards project completion in the coming months!
Last week, the contractor completed the Stage 3 pavement and concrete removal, excavation, temporary driveway installations and began the remaining storm sewer installation. In the coming weeks, the contractor will complete storm sewer installation west of 7th Street, continue miscellaneous removals, roadway excavation, and begin preparing for curb installation. |
Archived Construction Updates
Spring 2025Spring 2024 |
Summer 2024 |
Fall 2024 |
Contact Information
Christopher B. Burke Engineering, Ltd.
Dan Schroeder, PE Phone: (224) 315-0185 Email: [email protected] |
© Copyright 2025 City of Lockport, Illinois
|