Project Progress Paves the Way!
Last week, the contractor removed pavement and curbs, excavated earth and installed aggregate base course on the new roadway. This base forms the first layer for the new roadway. The contractor also installed the underdrain and poured concrete for the new curb throughout the project site.
This week, the contractor continues installing new curbs and will begin preparing for sidewalk and driveway installation once all curbs are complete. The first layer of asphalt in Stage 1 is scheduled to begin Monday, April 21st. |
Remember that all businesses in the area are open and fully accessible during construction!
Change in traffic! Refer to the map below
Project Phases
Project PhotosCrews have been busy installing sanitary sewer improvements, water valves and temporary pavement! |
|
Contact Information
Christopher B. Burke Engineering, Ltd.
Dan Schroeder, PE Phone: (224) 315-0185 Email: [email protected] |